Integration of Oracle Fusion Projects and Oracle Primavera P6
Learn about how Emerald helped with an Oracle Fusion integration


Client Overview
Large contractor in the Philippines needed a better way to manage costing and forecasting processes for dozens of multi-year projects in five different industries, including very large and critical infrastructure projects.
Challenges
-
Having one consistent system across the business units, giving transparency to management on progress
-
Getting forecasting done every week on all projects
-
Managing manpower and critical equipment requirements from all jobsites for best performance
-
Accurate reporting of progress to date and forecasting of estimates to complete on the project tasks
-
Managing estimates and budgets with actual progress in the field to have a clear understanding of actual progress to date
Results
-
Integrated Oracle Fusion Projects and Oracle Primavera P6
-
Standardized strategy on project WBS, project task details, project resources, and project expenses
-
All calculations and integrations accommodate hours and costs. Set up multi-currency reporting for ledger and project based reporting.
-
Control of overheads and profits within P6, and control of resource rates to the project
-
Automatic updating of forecasting integrated from actuals from Oracle Fusion, and then updates from the field in P6
-
Time savings for actuals management and forecasting updating