Skip to main content

Articles in Category: Primavera P6

ZOHO-P6 Integration

When a new client request comes in, you can create a project from ZOHO CRM. For us projects come in several categories and we have task list templates ready to be used to create tasks to charge to. Typically the first task list is Business Development. We kick off with that and assign the team working on the initiative. We can then send the project, the task list, the tasks and the resources into P6. We can do that in one step or two depending on the task list development. In this case we have a good idea of the scope of work and were able to put it together with 2 task lists. So we can integrate bot the project and the WBS/tasks and resources right away. So we use a really simple user interface tight in ZOHO projects to kick this off into P6. We tell the integration to send both the project and WBS over. Once that is done, we can go into P6 and start actionining the work. We also get a message letting us know if there were any issues with the intgration, such as a duplicate project exisiting. If all is good, you should get a PASS message both for the project and for the WBS.

Large XER Files do not play well with P6 Import and Export

Are you finding when you are importing or exporting a large number of projects that not all the projects are coming across when they are imported?

While converting a client from P6 V8.3 to V15.2, we found the data was not always transferred completely when we migrated large numbers of projects. Instead, with XER file sizes larger than 100,000 KB not all projects were exported and/or imported. We confirmed this recently on a subsequent project with a different client where we were migrating projects from P6 V7.3 to V17.12 and encountered the same issue.

In the first case, we exported the projects using an XER. Our file was over 300,000 KB. We found 4-5 projects were not exported. When we imported the same file, there were 2-3 additional projects that were not imported to the new database.

We looked at additional files for the same client and found that in XER files with a size larger than approximately 100,000 KB there were several projects in each XER missing when the file was imported.

Once we reduced the number of projects in the exported XER files to keep the file size under 100,000 KB, we found no projects were lost and our data was accurate.

Keep an eye on XER files larger than 100,000 KB when importing and exporting, they may not have complete data in them once they are imported.

Exactly Which Projects Are Using Each Global or EPS Activity Code?

In P6, identifying which projects are using each Activity Code in a quick, consolidated, easy to use manner is challenging. Especially when you consider some clients have a LOT of baselines.

But is this is r-e-a-l-l-y information we need to be able to capture? In my experience, there are a number of scenarios where that answer is a resounding “Yes”! One common example – the Activity Codes Dictionary needs to be cleaned up.

Moving Time in Team Member - EASY

When you are working on a project and you move from Project into Support, sometimes it is hard to decide the exact cutoff point for the project team to start charging to the new support project. I had a problem the other day where I needed to decide the end date and cut over. The client selected a date a few weeks before we had thought we were going to cut it off after she checked her budgets and we realized we were going to go over.

So I had to go back to look through the timesheets we had submitted in Team Member to get the time reallocated before sending it into our QuickBooks where we invoice from.

Are You Tracking Ideas? Are Approved Ideas Easily Translated into Project Proposals?

Ideas in Oracle Prime:

Use Oracle Prime to create ideas: capture, evaluate, and process the ideas for new initiatives and business endeavors.

Ideas are processed using a submission and approval workflow. Prime Projects provides a default workflow for processing ideas, or you can create a customized workflow. First the idea creator creates an idea and specifies the idea's business case. When an idea contains sufficient information, the creator can submit the idea for further processing by routers and owners.

P6-QA and the Project Scheduler

Manually wading through a schedule and looking for errors is time consuming and prone to human error. Not only that, it's boring. No one wants to do it, but you need to check your schedule for errors!

Even worse then working through your own schedule for errors, is slogging through a contractor's. When you don't know how they have built the schedule, it can take days to make sure things hold together. Some of our clients have several layouts, reports and even special access databases and outside tools to do this which is very time consuming, error prone and boring.

Finding Setting Up or Changing Resource Availability in P6 a Struggle?

We have all experienced at one point or another how tedious (and time consuming) setting or changing resource availability can be in the P6 resource dictionary. Particularly for an example like the one we will walk through where you are setting up or adjusting turnaround resources and the weekend rule happens to be ½ crews.

P6-Loader can ease the pain of these types of tasks.

Do You Need EV Calculated at the Resource Level?

You are correct; out-of-the-box P6 does not calculate Earned Value (EV) at the resource assignment level. It only runs EV at the activity level which is fine for a start, but what to do when you need to 'dig deeper' and analyze crew performance? You can't use Global Change to calculate the resource assignment EV because the activity percent complete isn't available in the Global Change list of fields.

A very simple option is to use TAPS to input your schedule updates. TAPS is P6 updating using barcodes (plus additional functionality). By using TAPS, updates are faster and more accurate giving you (and your team) more time for schedule analysis. Yes, TAPS runs EV calculations at the resource level.

P6-Loader Usage Sheets Revolutionize P6 Database Maintenance

When you have a large number of users in your P6 database, it is surprising how quickly that database can get “clogged up” with a lot of unwanted data. This happens even when using Sandbox databases, restricting privileges and every other trick you have thought of; long time P6 users know what I am talking about.

A Guide to P6 Archiving - Part 2

Archiving P6 Project Data and the Question of Location

This is part 2 of a series of blogs discussing best practices of P6 archiving. In Part 1 we discussed the question of time:

  • How long should you keep a P6 project file?
  • How do you track the date to archive your P6 project?

Now we will discuss the question of location.

archive project data

A Guide to P6 Archiving - Part 1

Archiving P6 Project Data and the Question of Time

We get asked on a regular basis what the best way to archive P6 data is.

  1. How long should a project file be kept?
  2. What should be done with the project files when that time period has expired?
  3. Where should they be kept?
  4. How can we retrieve if we need them, especially with upgrades?

In this blog series, we’ll look at some of the options available to a P6 user and discuss the question of time.

Archiving P6 Project Data and the Question of Time

How to Publish P6 Project Data - Now That You Have To

In Primavera P6 16.x and Beyond You Need to Publish Your Project Data for Resource Analysis and a Whole Lot More

When working with resources in Primavera P6 Web version 16.x on, there is a new twist: the need to publish data. If you are trying to analyze resources and the following message displays, it's time to publish.

P6 Warning - Resources Don't Have Published Data

This Job Site Really Needs Help!

Addressing Primavera System and Connectivity Issues

Over the last few years I have worked with many clients on turnaround projects in remote trailers on job sites that didn't have great connectivity. Now I am no techie, so I cannot pinpoint what causes the problem, but I know there is a problem when the coffee maker is the busiest place in the trailer. Now I am talking trailer coffee here folks, that stuff is gut rot at the best of times. If the planning team is hanging around, it is because they have been kicked out of Primavera P6 again!

Primavera P6 Connectivity

In the current economy the mere suggestion of financial spends to address system issues are something that will elicit gasps, face palms and shocked facial expressions, let alone a few choice words. But during one of these “extended coffee breaks” I did some number crunching out of curiosity on what the downtime costs really were.

Team Member - P6 Version 16.2

There Are Some Great Improvements To Talk About

As longtime users of Primavera P6 and Timesheets, we were pleasantly surprised to see some great improvements in the timesheets part of P6 v 16.2. The approval portal, which used to be very hard (I would even say impossible) to work with, is now much easier. Oracle has particularly improved the ability to find what timesheets need approval, and there is better adherence to layered approvals by the resource and project managers. Both of these tasks used to be ordeals in the previous versions.