P6 Activity Codes as a Source of Gantt Bar Configuration
I have often been asked the question – ‘can I have my schedule activity bars automatically appear a specific color and/or pattern according to the value of a specific code?’ Yes, you can do this very easily.
Let’s look at one simple example.
Above I have incorporated additional bar configurations along with the default Critical Remaining Work and Remaining Work configurations.
The additional bar configurations are generating the hatching by filtering on the activity code used to assign the ‘Engineering’ and ‘Construction’ grouping in the layout.
Written by Mary Lynn Backstrom, PMP, PMI-SP, PMI-BA – Implementation Specialist
on Tuesday, 19 January 2016.
Posted in All Articles, Primavera P6
After I wrote my last blog, a co-worker asked me why I would want to store period actuals in the data warehouse when it seems as though I can get the same value from the historical data in the data warehouse.
Both Oracle’s Primavera Analytics and our P6-Reporter (previously EP-datawarehouse) support capturing some kind of historical data – data that shows what the information in P6 looked like at some point in the past. It’s fairly easy to see how this historical data can be exploited to produce information that is in concept very similar to what you get from the financial period actuals.
Written by Dan MacMillan - Integration Specialist
on Wednesday, 30 December 2015.
Posted in All Articles, P6-Reporter, Primavera P6
Are you getting broken WBS elements, WBS elements appearing as projects or errors such as "is not a valid integer" when migrating?
Recently, while converting a client from P6 r8.3 to r15.2, we had to move a number of baselines to the new database. We used our P6-Loader to unassign and detach the baselines from the current project and then created XER’s to move them to the new database.
To our surprise, when we imported the baselines as projects into the new 15.2 database, the WBS elements were all messed up. Instead of one project with many WBS elements, our project appeared as many different projects, one per WBS, all with the same Project ID. They also appeared outside the EPS structure and P6 wouldn’t let us move them into the correct EPS node. Every attempt gave us the error that “ is not a valid integer value”.
Written by Ian Nicholson, P.Eng. - VP Solutions
on Wednesday, 30 December 2015.
Posted in All Articles, P6-Loader, Primavera P6
Primavera Analytics supports financial periods – but what does that actually mean?
P6 Time Distributed Data
P6 has two main sources of time-distributed data, spread data and financial period actuals. The main difference between these is that spread data is calculated, while financial period data is stored. This difference impacts both how accurate the data is and how flexibly it can be viewed.
Written by Dan MacMillan - Integration Specialist
on Wednesday, 23 December 2015.
Posted in All Articles, Primavera P6
We often have clients ask us the most efficient way to change out resource assignments. This often happens when work that is expected to be assigned to one resource gets assigned to another.
For example – I want to change the resources in a particular plant from my own staff and assign it to a contractor. In this simple example, I have decided to give all the trade work in one plant to Jacobs instead of performing with my own labor force. I want to remap the resource assignments as follows:
Written by Ian Nicholson, P.Eng. - VP Solutions
on Monday, 22 February 2016.
Posted in All Articles, P6-Loader, Primavera P6
New Hidden Refresh Key Combination in P6 Professional (Optional Client) Version 8.x and 15.x
A client who we are currently upgrading to P6 v 15.1 has been complaining that the refresh is not working properly in P6 Professional (aka The Optional Client). This client had no issues with release 7.x.
We did some testing and found the same thing. Sometimes hitting F5 doesn’t reliably get a refresh.
Written by Ian Nicholson, P.Eng. - VP Solutions
on Wednesday, 16 December 2015.
Posted in All Articles, Primavera P6
How to easily and safely scrub XER’s of the POBS records in your Primavera P6 Database
We have had a number of complaints recently about the POBS imports really slowing down XER import performance and also complaints that the XER files coming out of Primavera P6 are huge.
Written by Ian Nicholson, P.Eng. - VP Solutions
on Monday, 14 December 2015.
Posted in All Articles, Primavera P6
P6 has three substring commands that can be invoked from within Global Change
Very few people realize that there are substring commands available in the P6 Global Change function (available in the P6 Client only).
Recently in a LinkedIn P6 group, a member was asking for help in renaming an activity UDF assignment. He had a large number of activities that he needed to change the UDF prefix on because of a plant renumbering. He had an existing UDF called Equip_ID and he needed to remove whatever the first character is and replace it with a ‘2’.
Written by Ian Nicholson, P.Eng. - VP Solutions
on Tuesday, 01 March 2016.
Posted in All Articles, Primavera P6
The Emerald team just completed a client migration to the Oracle Primavera SaaS Cloud. The client had over 1000 small (50-60 activities) projects in their on-premise Primavera P6 PPM v8.3.2. They needed to be able to share the projects for the next 2 years amongst a large collaborative program team with multiple contractors and engineering firms. This program is very high profile and reporting is paramount.
Written by Nicole Jardin, P.Eng. - CEO
on Friday, 11 December 2015.
Posted in All Articles, P6-Loader, Primavera Cloud, Primavera P6
How the P6-Loader Makes Life Easy When Working With P6 Resource Assignments and Resource Dictionaries
Working with P6 resource assignments and resource dictionaries can be extremely time-consuming. The task becomes especially tedious when it comes to planning a turnaround project with multiple daily shifts and varying crew sizes on day and night shifts, or a capital project where you have rotating work shifts with crews overlapping on the back shift.
on Monday, 09 November 2015.
Posted in All Articles, P6-Loader, Primavera P6
We have been using v15.2 of P6, both EPPM and PPM, for 2 weeks now. I personally use the client or PPM the most. This version has been upgraded to 64 bit, and I can really see the difference in speed.
Written by Nicole Jardin, P.Eng. - CEO
on Friday, 30 October 2015.
Posted in All Articles, Primavera P6
Adjusting Primavera P6 Settings and Structures with the P6-Loader
We recently had a support call from a client that started having performance issues with their P6 database during the pre-work phase of their turnaround. We looked at the Oracle 11.2.0.4 enterprise database and found a massive amount of archive logs being chewed up. In fact, it was on a scale of 1-2 GB of logs within 2-5 minutes on average. With that kind of volume it would not take long for a server to receive the dreaded Oracle error message ORA-00257: archiver error. When this happens the database usually needs more space on the device where the archive log files are stored, which results in the database not allowing any more transactions until the issue is corrected.
Written by Paul Jardin - VP of Technology
on Thursday, 22 October 2015.
Posted in P6-Loader, Primavera P6
A comparison of the Primavera P6 Import and Export Functionality and Emerald's P6-Loader
The P6-Loader is a unique Primavera enhancement tool developed by Emerald for the secure movement of data between Primavera P6 and Microsoft Excel. Many users are aware that P6 already has some built-in functionality, which is why I often hear this question from my students, as well as from my clients: How is the P6-Loader different from the built-in import and export functionality in P6 Client?
There are numerous differences between the two when it comes to choosing the right tool for importing/exporting your P6 data. Here are some of the main points to consider:
on Tuesday, 13 October 2015.
Posted in P6-Loader, Primavera P6
A step-by-step guide with screenshots
There has been a lot of excitement around the Emerald office with the release of Primavera P6 15.2. Emerald has been a Primavera partner for over two decades now and have come to learn that with each release there are some good surprises. Thanks goes out to Karen Pilla and the Oracle team for driving the next phase of developments on a mature product that helps project managers run some of the largest and smallest projects around the globe.
Written by Paul Jardin - VP of Technology
on Thursday, 08 October 2015.
Posted in Primavera P6
Watch Out For The Build Number
There are some issues that we observed when upgrading from the 15.1 release of Primavera P6 to version 15.1.6. When we ran the setup.exe file for P6 15.1.6 it did not change the build number after we logged into P6 client.
Written by Paul Jardin - VP of Technology
on Tuesday, 06 October 2015.